Yorke Drive Focus

Development of the Yorke Drive estate and Lincoln Road playing fields in Newark.

Construction timeline

The Yorke Drive Regeneration Project is entering an exciting new phase, with construction works starting in October 2026. The regeneration will transform the estate through the delivery of new affordable and market homes, improved green spaces and better sports facilities.

Key Milestones

October until December 2026

  • Start on site.
  • Installation of site compound, fencing and safety measures.
  • Site clearance and preparation works.
  • Demolition of the existing pavilion, garages and 4 residential properties.

January 2027

  • Construction begins on the first affordable homes.

Remainder of 2027

  • First affordable homes completed and ready for residents.
  • Phase 1 decants completed, enabling existing residents to move into new homes on the estate.
  • Continued delivery of affordable homes across the development.

2028

  • Completion of all affordable homes.
  • Demolition of the remaining properties within the regeneration area.

2029 onwards

  • Delivery of market sale homes.
  • Completion of the wider Yorke Drive Regeneration Project.

Please note that construction programmes can change and dates may be updated as the project progresses.

Site security and safety

The safety of residents, visitors and construction workers is our highest priority throughout the regeneration programme.

Through our Resident Charter, Newark and Sherwood District Council, Compendium Living and Lovell have committed to ensuring that construction works are managed safely, securely and with minimal disruption to the community.

Our commitments

We will:

  • Ensure all demolition and construction works are properly planned and carried out safely.
  • Comply with all relevant health and safety legislation and industry standards.
  • Use appropriately qualified contractors and subcontractors.
  • Maintain secure site compounds and construction areas.
  • Provide clear signage and safe pedestrian routes around works.
  • Keep residents informed about works that may affect access, parking or local services.

Site security

To protect both the site and the surrounding community, security measures are expected to include:

  • CCTV monitoring of construction compounds.
  • Secure site fencing and hoarding.
  • Out-of-hours monitoring and reporting arrangements.
  • Liaison with the Police where required.
  • Additional security measures during school holidays and high-risk periods if needed.

Reporting concerns

Residents will be provided with dedicated contact details for the regeneration and site teams should they need to report any concerns relating to construction activity, site safety or security. Contact details will be displayed on site hoarding, newsletters and project communications.

Minimising disruption

We recognise that construction activity can cause disruption. Through the Resident Charter, Lovell and NSDC have committed to reducing the impact on residents wherever possible.

This includes:

  • Traffic management plans to control construction vehicles.
  • Careful scheduling of deliveries where possible.
  • Regular road sweeping and cleaning.
  • Prompt removal of mud and debris.
  • Monitoring of dust levels and implementation of dust suppression measures.
  • Maintenance of site fencing and hoarding.
  • Daily checks of footpaths and pedestrian routes.
  • Continued management of vacant properties and estate maintenance throughout the regeneration programme.
 

Communications and resident engagement

Keeping residents informed and involved throughout construction remains a key priority.

The Yorke Drive Regeneration Project has always been shaped by resident feedback, and this will continue through the Resident Charter.

How we will keep you updated

Residents can stay informed through:

  • Monthly updates on the Yorke Drive webpage.
  • Regular regeneration newsletters delivered to homes.
  • Quarterly Yorke Drive Residents Panel meetings.
  • Social media updates where appropriate.
  • Written updates regarding significant milestones and upcoming works to households.
  • Creation of drop-in sessions for residents to ask the Regeneration Team questions (more details below).

Resident drop-in sessions

From November 2026 to February 2027, members of the Regeneration Team will be holding regular drop-in sessions at Beaumont Walk Community Centre.

This is an opportunity for residents to ask questions, receive project updates, discuss any concerns, or find out more about the Yorke Drive Regeneration Project. No appointment is needed.

Location: Beaumont Walk Community Centre

Session dates and times

November 2026

  • Monday 2 November, 2:00pm to 6:00pm
  • Wednesday 25 November, 9:00am to 12:00pm

December 2026

  • Monday 7 December, 2:00pm to 6:00pm
  • Wednesday 23 December, 9:00am to 12:00pm

January 2027

  • Monday 4 January, 2:00pm to 6:00pm
  • Wednesday 20 January, 9:00am to 12:00pm

February 2027

  • Monday 1 February, 2:00pm to 6:00pm
  • Wednesday 24 February, 9:00am to 12:00pm

We look forward to seeing you there and answering any questions you may have.